| Payment period ends | Saturday 31 October 2026 |
|---|---|
| Payment due (7 days later) | Saturday 7 November 2026 |
| Payment notice by (5 days after due) | Thursday 12 November 2026 |
| Pay less notice by (7 days before final) | Tuesday 17 November 2026 |
| Final date for payment (17 days after due) | Tuesday 24 November 2026 |
When is a payment notice due?
Not later than 5 days after the payment due date. It must state the sum the payer considers due and how it was worked out, and the sum can be zero.
Free, with no sign-up. Everything is worked out in your browser: nothing you type is sent to us or stored. A guide, not legal advice. Based on the Scheme for Construction Contracts (England), as read on 31 October 2026. Your contract's own periods come first.
Payment notice dates
Enter the end of the payment period, and the date the claim was received if it came later. The periods below are the Scheme's defaults: change them if your contract sets its own.
Change the periods to match your contract
- Payment due
- Payment notice by
- Pay less notice by
- Final date for payment
More questions
- When must a pay less notice be sent?
- What is the final date for payment in construction?
- See how SUBR works
Sources
The rates, thresholds and dates on this page come from these official sources, read on 31 October 2026.
- legislation.gov.uk: Scheme for Construction Contracts (England and Wales) Regulations 1998, Schedule
- legislation.gov.uk: Housing Grants, Construction and Regeneration Act 1996, Part II
- legislation.gov.uk: Section 110B, when no payment notice is given
- legislation.gov.uk: Section 112, the right to suspend work
- legislation.gov.uk: the Scottish Scheme, SSI 2011/371
- legislation.gov.uk: the Northern Ireland Scheme, SR 2012/365
- legislation.gov.uk: the Welsh regulations, SI 2011/1715
Where SUBR comes in
SUBR is AI software for UK contractors who send work out to subcontractors. Its AI reads your client quote, your office names each trade's share, and SUBR builds every scope with your costs, margin and client price left off it. Each subcontractor answers on their own link and sees only their own price.
See it on a quote
A short call. We walk a dummy quote from PDF to jobs on site.